Skip to content

ASR Bridge Repair

by Webmaster on April 19th, 2008

With a rush order request the Atlantic Shoals bridge dept. contacted  the bridge & dock building subsidiary of the  Arcadia  Terminal  Street and Dock  Railroad for a replacement bridge. At 11:50 hr. on  April 19, 2008 the Arcadia Terminal bridge building dept. placed an order for the steel to fabricate a replacement structure. The steel company stated that the rush order should take around 7 days and will ship the bridge components by rail to the Arcadia Terminal on or around April 26, 2008. Actual fabrication of the bridge will start after the receipt of materials and an on site engineering evaluation by the Arcadia Terminal engineering staff. Completion date TBD.

P. Laier
Engineering Manager
Arcadia Terminal R.R

Comments are closed.